2019

Akita & Noshiro OWF

CLIENT: Kajima Corporation

ROLE: T&I Project Manager

SCOPE: Transport from Europe to Japan of 33 MPs and TPs and Installation Offshore (MPs and TPs) in Akita and Noshiro (Japan)

Project management, risk interfaces. Responsible for early phase concept engineering to full mechanical completion. Preparation of Method Statements, Risk Assessments, emergency response plans and safe working procedures. Implementation of requirements from MLIT during and before construction phase. Lead client approval and project certification by Japanese Class-NK.

Albatros Project – North Sea

CLIENT: Deme Offshore

ROLE: Lead roject Engineer for TP installation

SCOPE: Installation of TPs and ACs with Sea Installer (A2Sea, Deme Offshore)

Vessel planning, daily progress reports and PtW applications. Responsible for early phase concept engineering to full mechanical completion. Preparation of Method Statements, Risk Assessments, emergency response plans and safe working procedures. Implementation of German SchuSiKo during and before construction phase. Daily site coordination, planning, reporting and managing multidisciplinary subcontractors

Hohe See & Albatros Project – North Sea

CLIENT: Deme Offshore

ROLE: Lead Project Engineer & Offshore Installation manager

SCOPE: Installation of MPs from HLJV Innovation

Development of Noise Mitigation Concepts for German Waters (DBBC and NMS). Responsibility for design and fabrication of sea- fastening and installation tools for
MP, TP and AC installation. Preparation of installation method statements and risk assessments. Creation of deck-layouts and lifting plans.

Hohe See & Albatros Project – North Sea

CLIENT: Deme Offshore

ROLE: Lead Engineer for MP installation vessel mobilization

SCOPE: Innovation Mobilization

Lead engineer for sea-fastening and installation tools for HLJV Innovation in Vlissingen Netherlands. Managing subcontractors on vessel (steel fabricator, hydraulics, special purpose equipment) as well as project crew.

Hohe See & Albatros Project – North Sea

CLIENT: Deme Offshore

ROLE: Lead Engineer

SCOPE: Retrieval of foundations and installation equipment with shear leg Gulliver from Pacific Osprey

After a crane accident onboard the main installation vessel Pacific Osprey from SBO all project equipment including foundations as well as NMS and lifting tools had to be recovered from onboard Pacific Osprey by means of a feasible crane vessel (Gulliver). Lifting engineering and method statements as well as a contingency plan have been developed.

Hohe See Project – North Sea

CLIENT: GeoSea NV

ROLE: Lead Project Engineer & Offshore Installation manager

SCOPE: Installation of MPs, TPs, ACs from Pacific Osprey

Offshore Installation manager for Transport & Installation of Monopiles (MPs), Transition Pieces (TPs) and Anode Cages (ACs) with Heavy Lift Jack-Up vessel Sea Pacific Osprey (Swire Blue Ocean).

Hohe See Project – North Sea

CLIENT: GeoSea NV

ROLE: Lead Project Engineer and Site Manager

SCOPE: Mobilization of Installation vessel Pacific Osprey

Lead of mobilization works for sea-fastening of MPs, TPs and ACs as well as project installation equipment.

Coordination of subcontractors and daily planning of lifting and welding works.

Hohe See Project – North Sea

CLIENT: GeoSea NV

ROLE: Lead Project Engineer and Method Engineer

SCOPE: Installation Planning and engineering and logistics

Preparation and development of logistic barge feeder concept for transportation of foundation from Rotterdam to Eemshaven. Responsible for design and fabrication of sea-fastening for main installation vessel and barges. General project preparation for  installation vessel (Pacific Osprey) including deck-layouts, lifting drawings, Method Statements, ITPs, Risk Assessments etc.

2019
2016

Baltic 2 Project – Baltic Sea

CLIENT: Hochtief Solutions AG

ROLE: Offshore Installation Manager

SCOPE: Jacket installation with Stanislav Yudin

Installation of Jackets for the BALTIC 2 project with floating crane vessel Stanislav Yudin (SHL). Lifting of jackets from barges (offshore feedering, offshore lift).

Baltic 2 Project – Baltic Sea

CLIENT: JV Hochtief Solutions AG & GeoSea NV

ROLE: Offshore Installation Manager

SCOPE: Jacket installation with sheerleg Taklift 4

Installation of Jackets for the BALTIC 2 project with sheerleg Taklift 4 (Boskalis). Load-out of jackets in Sweden,  Trelleborg.

Baltic 2 Project – Baltic Sea

CLIENT: JV Hochtief Solutions AG & GeoSea NV

ROLE: Project engineer

SCOPE: Jacket installation and logistic concept

Jacket installation, including pre-piling  (includes preparation phase, installation, grouting and remedial works). Management of nearshore and offshore logistics of barge feeder concept, vessel selection and BIMCO contract negotiations. Follow-up on MWS and BSH comment sheets. Creation of Safe Working Procedures, RAs and general project documentation.

Baltic 2 Project – Baltic Sea

CLIENT: JV Hochtief Solutions AG & GeoSea NV

ROLE: Naval Architect

SCOPE: WTG installation consultancy for marine document package

Preparation of all engineering calculations for WTG package, including of Motion Analysis, loading plan, hydrostatics and lifting engineering.

Processing of MetOcean data and workability calculations and stochastic.

2016
2016

Global Tech 1 – North Sea

CLIENT: Employee at Hochtief Offshore

ROLE: Naval Architect and marine consultant

SCOPE: Project consultant for marine related topics

Dynamic lifting analysis for tripod installation, Motion Analysis, deck-layouts and vessel positioning drawings.

Ballasting and load-out calculations for WTG logistic scope.

Responsible for model tests of gravity based foundation (Gravitas) projects, floating foundations (BlueH) as well as ship model tests of jack-up vessels.

Vessel design and calculations Innovation and Thor

CLIENT: Employee at Hochtief Solutions AG

ROLE: Naval Architect

SCOPE: Innovation transit design criteria and Thor stability booklet for vessel conversion

✓ Hydrostatics and stability of Innovation (Thor and Innovation vessel operational manual) according to DNV, MODU and IS code.
✓ Motion Analysis for HLJV vessels and barges including Air Gap calculations. Dynamic Lifting Analysis for offshore lifts.
✓ Hydrodynamic Analysis of offshore floating foundations. Coding and automation automatic (Python and Matlab).

2016

Contact